Update #4: Reconstruction Phase 1A
The City has received a schedule from our deep utility contractor, Castle Rock Enterprises, for Phase 1A. Starting the week of May 26, Castle Rock will start mobilizing equipment, conducting bird nest surveys, and completing tree and boulevard removals.
Shallow utility work by ATCO Electric's contractor, Arctic Backhoe, is scheduled to start June 2 for a duration of approximately three weeks. Once shallow utilities are complete, Castle Rock will start on deep utilities in July.
Garth Gallant, Castle Rock’s Public Liaison, will be in direct contact with Hillcrest residents during Phase 1A of construction. Phone: 780-878-4825 / Email: Garth@castlerockent.com
Residents may still reach out to the City directly for any further questions or concerns. Phone: 867-689-1548 / Email: Gareth.Earl@whitehorse.ca.
Fridays in the Park: May 30
Engineering staff will be at Hillcrest Park to answer questions regarding the Hillcrest Reconstruction project during the City's Fridays in the Park event.

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends