Share Update 5: Reconstruction Phase 1A on Facebook
Share Update 5: Reconstruction Phase 1A on Linkedin
Email Update 5: Reconstruction Phase 1A link
Thanks for attending Fridays in the Park on May 30! Engineering staff had a table set up and we had lots of good discussion with residents regarding Hillcrest reconstruction.
There were a few questions about the extents of tree clearing in Phase 1A and if there would be any sidewalks. Attached is a drawing showing the limits of tree clearing, which is now complete.
The project originally included tree clearing along Summit Road, south of Roundel, but that has since been removed. We are revising the design to re-align the road to preserve those trees in that area.
Also attached is a signage and line painting plan for Phase 1A. As indicated, there is no sidewalk being installed in this phase, due to narrow right-of-ways. We are currently working on a revision to this drawing that will see barrier curb installed along the southwest side of Summit, to help retain the slope. The re-alignment to preserve trees is not currently shown.
For information regarding sidewalks and general conceptual design for future phases, please download a copy of the What We Heard 2: The Roadmap report on this page.
Thanks for your interest in the project and stay tuned for more updates as we progress through construction.


Share Update #4: Reconstruction Phase 1A on Facebook
Share Update #4: Reconstruction Phase 1A on Linkedin
Email Update #4: Reconstruction Phase 1A link
The City has received a schedule from our deep utility contractor, Castle Rock Enterprises, for Phase 1A. Starting the week of May 26, Castle Rock will start mobilizing equipment, conducting bird nest surveys, and completing tree and boulevard removals.
Shallow utility work by ATCO Electric's contractor, Arctic Backhoe, is scheduled to start June 2 for a duration of approximately three weeks. Once shallow utilities are complete, Castle Rock will start on deep utilities in July.
Garth Gallant, Castle Rock’s Public Liaison, will be in direct contact with Hillcrest residents during Phase 1A of construction. Phone: 780-878-4825 / Email: Garth@castlerockent.com
Residents may still reach out to the City directly for any further questions or concerns. Phone: 867-689-1548 / Email: Gareth.Earl@whitehorse.ca.
Fridays in the Park: May 30
Engineering staff will be at Hillcrest Park to answer questions regarding the Hillcrest Reconstruction project during the City's Fridays in the Park event.
Share Update #3: Reconstruction Phase 1A on Facebook
Share Update #3: Reconstruction Phase 1A on Linkedin
Email Update #3: Reconstruction Phase 1A link
Phase 1A of the Hillcrest Reconstruction project is starting in Spring 2025.
Work in Phase 1A will focus on:
- Deep and shallow utility upgrades along Roundel Road (west of Summit Road)
- Replacement of the sanitary main under the Summit Road greenbelt
- Re-surfacing of Summit Road south of Roundel Road
The current timeline for Phase 1A work is
- May 2025: boulevard removals and tree clearing to prepare construction sites.
- June to July 2025: Shallow utility upgrades in conjunction with ATCO Electric Yukon and Northwestel.
- July to October 2025: Deep utility upgrades.
- 2026: Phase 1A road re-surfacing, landscaping, general restoration, and planning for Phase 1B.
Continuing in May 2025, City staff will engage with residents in and around Phase 1A to provide information about work plans, schedule, temporary utility disruptions, and temporary access and parking.
Thank you in advance for your patience and understanding while this work is underway.
If you have any questions regarding the project, please contact the Engineering Services Department at engineeringservices@whitehorse.ca.
Share Update #2 Regarding 2024 Construction (Phase 1A) on Facebook
Share Update #2 Regarding 2024 Construction (Phase 1A) on Linkedin
Email Update #2 Regarding 2024 Construction (Phase 1A) link
Dear Hillcrest residents,
The City has been working hard to advance implementation of Phase 1A of the Hillcrest Reconstruction project which includes Roundel Road and the Summit Greenbelt Area.
Below are some key updates regarding Phase 1A progress:
• Notification has been received that federal funding is available for the reconstruction of the public water and road infrastructure through the Investing in Canada Infrastructure Program (ICIP).
• A YESAB project application is in progress (Adequacy) to move forward with a land use permit required to reconstruct within the Summit Greenbelt and other areas within Yukon government lands.
• The schedule for construction of deep utilities on Roundel Road has been delayed, and is now expected to start in May of 2025. This is due to schedule conflicts with relocation of existing overhead and buried power within the right of way.
• The City has prepared an agreement form for the Roundel Road property owners that indicated they would like to take part in the opt-in program to have the Phase 1A civil contractor replace their private water and sanitary connections. This agreement will be delivered by hand in late June, early July.
Thank you for your understanding as we work to advance this complex reconstruction project.
If you have questions regarding this update please contact Taylor Eshpeter at Taylor.Eshpeter@whitehorse.ca.
Share Update Regarding 2024 Construction (Phase 1A) on Facebook
Share Update Regarding 2024 Construction (Phase 1A) on Linkedin
Email Update Regarding 2024 Construction (Phase 1A) link
Construction of Phase 1A of the Hillcrest Reconstruction Project is planned to commence in summer of 2024. Phase 1A includes reconstruction of Roundel Road (west of Summit Road) and the sanitary main that passes under Summit greenbelt (map attached).
The scope of Phase 1A is reduced from the original Phase 1. This means that residents who were impacted within the previous Phase 1 along Sunset Drive North and Summit Road North will not be impacted until a later phase.
Please contact Rob Dickson at robert.dickson@whitehorse.ca if you have questions regarding the upcoming construction.

Share What We Heard #2: The Roadmap on Facebook
Share What We Heard #2: The Roadmap on Linkedin
Email What We Heard #2: The Roadmap link
What We Heard: The Roadmap presents the results from Phase 3 of the public engagement program where we presented a Draft Concept and received feedback and ideas from residents.
Click here to view the report.
Share What We Heard #1 on Facebook
Share What We Heard #1 on Linkedin
Email What We Heard #1 link