Update 6: Reconstruction Phase 1A

The Hillcrest Reconstruction Project Phase 1A is well underway. Here’s what to expect in the coming weeks:

July 17 to 24
Intersection of Roundel Road and Summit Road will be closed for construction, except for emergency vehicles. Residents are asked to please follow detour signage.

July 24 onwards
Construction will progress onto Roundel Road, between Summit Road and Sunset Drive North. During this time, temporary parking will be established in the greenbelt by the hockey rink and on lot 130. Access to the hockey rink has been temporarily upgraded with a granular crush surface – see route below. Please obey signage and only use this access if you are a resident of the active construction area.

The overall schedule of the Hillcrest Reconstruction project is anticipated to take roughly 10 years. There are five phases of work currently planned, with 2 years for each phase. Phases are planned as follows:

  • Phase 1A (2025-2026): Roundel Road (between Summit and Sunset Drive North), Summit greenbelt sanitary main replacement, Summit resurfacing (Roundel to Hillcrest Drive)
  • Phase 1B (2027-2028): Sunset Drive North (east end), Roundel Road (east of Summit), Burns Road (Roundel to Hillcrest Drive)
  • Phase 2 (2029-2030): Hillcrest Drive (hwy to Kluane Crescent east), Chalet Crescent
  • Phase 3 (2031-2032): Hillcrest Drive (Kluane Crescent east to west end), Kluane Crescent, Sunset Drive South
  • Phase 4 (2033-2034): Park Lane and Dalton Trail